Posted by & filed under Uncategorized.

DATE: Thursday, July 2, 2020

PROJECT TYPE: Roadway resurfacing project

LOCATION: The project is on Route 100 through the towns of Wilmington, Dover and Stratton. It begins in Wilmington at the intersection of East Main Street and North Main Street, and continues for 11.605 miles through the towns of Dover and Stratton, and ends near the Stratton-Wardsboro town line (near Penny Avenue).

TRAFFIC IMPACT: For the week of Monday, July 6 through Friday, July 10, between the hours 7 AM and 5 PM, motorists can expect alternating one-way traffic along the construction route in Dover and Stratton. Flaggers will be present to guide motorists through the work zone.

SPECIAL CIRCUMSTANCES/NOTICES: This week, construction activities include paving the final wearing course along Route 100 in Dover and Stratton, and installing permanent roadway signs in Wilmington, Dover and Stratton.

DURATION: Monday through Friday, 7 AM to 5 PM.

PROJECT COMPLETION: July 2020

Comments are closed.