The West Main Street project began construction on Monday, April 17 with Zaluzny Excavating performing the work.  Please note that the information provided below is subject to change as the week progresses due to weather or other unforeseen events.  We will do our best to keep everyone up to date with major changes.  Any driveway or walkway impacts will be scheduled with the individual property owner(s) at least 24 hours prior to the work occurring.

 

 

Anticipated Schedule – Week of 4/24:

Monday – Begin stone wall construction.  This work will continue throughout the week.  Install catch basin and drain pipe in front of Hayseed Gifts (if this work is not completed during the week of 4/17).
Tuesday – Install granite curbing on west end of project and in front of Hayseed Gifts.
Wednesday – Prepare sidewalk subbase on west end of project.
Thursday – Install concrete sidewalk on west end of project.
Friday – Cleanup on west end of project.
The westbound lane will be closed during the wall construction, curbing installation and sidewalk installation.  Flaggers will be controlling two-way traffic in the eastbound lane.
The traffic control with flaggers worked well this past week.  It may become more difficult next week as VTrans is beginning a project just west of the sidewalk project and will have the eastbound lane closed.  If problems begin to arise, we will work with VTrans to minimize delays and keep traffic moving through both construction areas.