Posted by & filed under Uncategorized.

DATE: Friday, October 18, 2019

PROJECT TYPE: Roadway resurfacing project

LOCATION: Route 100 through the towns of Wilmington, Dover, and Stratton. It begins in Wilmington at the intersection of East Main Street and North Main Street, continuing for 11.605 miles through the towns of Dover and Stratton, ending near the Stratton/Wardsboro town line (near Penny Avenue).

TRAFFIC IMPACT: For the week of Monday, October 21 – Friday, October 25, 2019, motorists should expect intermittent periods of alternating one-way traffic along the construction route. Flaggers will be present to guide motorists through the work zone and manage traffic.

DURATION: Crews will be working from 7 AM to 5 PM Monday, October 21, through Friday, October 25.

PROJECT COMPLETION: July 2020

SPECIAL CIRCUMSTANCES/NOTICES: Construction crews will continue shoulder stabilization and will start cleaning the worksite as the project begins to wrap up for the season.